from Chris Shook, superintendent of our building project:

 

The relocated gas line being has allowed us to complete the sanitary sewer installation. The City of Tulsa tested and approved the new work last week and we tied the existing building in on Saturday.

We also installed the new water meter and service to the sanctuary last week and that freed us to demolish the old. We are beginning the demo of the old gas, water and sanitary sewer lines and structures today and installing the new storm drainage as well.

Additionally, we have the concrete guys working on the footings around the perimeter of the community center and had our first concrete pour on Wednesday at 1:30.